SPP Wants to Defer $7B in 765-kV Projects to 2026

Tom Kleckner | Source: RTO Insider | Posted 10/15/2025

Keyword Tags:

SPP staff have reiterated their position to defer part of the RTO’s planned 765-kV transmission overlay, setting aside about $7 billion in regional projects from its 2025 transmission assessment.


AI generated summary

SPP staff have proposed deferring approximately $7 billion in planned 765-kV transmission projects to 2026, while seeking approval for up to 50 projects estimated at $11.16 billion. This decision comes as part of the 2025 transmission assessment, which reflects significant load growth in the region, necessitating a comprehensive evaluation of the transmission system. SPP's vice president of engineering, Casey Cathey, emphasized the importance of refining project details to ensure the grid can handle the increasing demand effectively and efficiently.

The deferral includes critical segments of the proposed 765-kV overlay, allowing for a more strategic approach to project planning. However, staff warned that excessive deferrals could complicate future assessments and disrupt modeling efforts. With new legislation in Oklahoma potentially introducing delays in construction permits, concerns have been raised about rising costs and the feasibility of completing these essential projects. The 2025 portfolio is expected to maintain a strong benefit-to-cost ratio, supporting reliability and addressing the challenges posed by escalating energy demands.



Link to Original Article

Please find the link to the full article below. (Please note that content provider might require a paid subscription)


Source Link: https://www.rtoinsider.com/117018-spp-wants-defer-7b-765kv-projects-2026/

Create a free trial account: Sign Up

Grid monitor is free to try. No credit card required


Already have an account? Login

Most Active PUCT Filings

APPLICATION OF ONCOR ELECTRIC DELIVERY COMPANY LLC FOR AUTHORITY TO CHANGE RATES - (115 filings)

APPLICATION OF SOUTHWESTERN PUBLIC SERVICE COMPANY TO AMEND ITS CERTIFICATE OF CONVENIENCE AND NECESSITY TO CONSTRUCT GENERATION RESOURCES AND ASSOCIATED FACILITIES IN TEXAS AND NEW MEXICO; FOR GOOD-CAUSE EXCEPTIONS; AND FOR RELATED RELIEF - (108 filings)

BROKER REGISTRATIONS - (94 filings)

PROJECT TO DEVELOP COA AND SPCOA STATEWIDE AVERAGE SWITCHED ACCESS RATES FOR NOVEMBER 2025 PUBLICATION UNDER PURA § 52.155 AND 16 TAC § 26.223 - (49 filings)

PROJECT TO SUBMIT EMERGENCY OPERATIONS PLANS AND RELATED DOCUMENTS UNDER 16 TAC § 25.53 - (33 filings)

APPLICATION OF ONCOR ELECTRIC DELIVERY COMPANY LLC TO AMEND ITS CERTIFICATE OF CONVENIENCE AND NECESSITY FOR THE DIVISION 138-KV TRANSMISSION LINE IN TARRANT AND DALLAS COUNTIES - (33 filings)

APPLICATION OF EL PASO ELECTRIC COMPANY FOR AUTHORITY TO CHANGE RATES - (31 filings)