MISO Discloses $280M Error, Over-procurement in 2025/26 Capacity Auction

Amanda Durish Cook | Source: RTO Insider | Posted 09/13/2025

Keyword Tags:

MISO said a yearslong software error caused it to clear more capacity than intended in past capacity auctions and which resulted in an approximate $280 million impact to market participants in this year’s auction.  


AI generated summary

MISO has disclosed a significant software error that led to an over-procurement of capacity in its 2025/26 Planning Resource Auction, resulting in an estimated financial impact of $280 million on market participants. The error, which had been undetected since 2017, was traced back to a third-party vendor's coding that incorrectly calculated the loss of load expectation (LOLE) using an 'all-hours' methodology instead of the tariff-defined 'daily peak hour' method. This miscalculation caused higher auction clearing prices and reserve margin requirements, affecting auctions dating back to the 2018/19 planning year.

In response to the error, MISO plans to transition to the all-hours LOLE methodology starting with the 2026/27 planning year, pending approval from FERC. While MISO will not retroactively adjust the clearing prices for the 2025/26 auction, it will issue settlement adjustments to affected market participants. MISO has also committed to enhancing its software validation and testing processes to prevent similar issues in the future, and it is currently notifying generation companies about the financial implications of the error.



Link to Original Article

Please find the link to the full article below. (Please note that content provider might require a paid subscription)


Source Link: https://www.rtoinsider.com/114585-miso-discloses-280m-error-procurement-2025-26-capacity-auction/

Create a free trial account: Sign Up

Grid monitor is free to try. No credit card required


Already have an account? Login

Most Active PUCT Filings

APPLICATION OF ONCOR ELECTRIC DELIVERY COMPANY LLC FOR AUTHORITY TO CHANGE RATES - (88 filings)

CY 2024 RETAIL ELECTRIC PROVIDER (REP) ANNUAL REPORTS AND CY 2025 REP SEMI-ANNUAL REPORTS PURSUANT TO 16 TAC 25.107(I) - (78 filings)

BROKER REGISTRATIONS - (75 filings)

CY 2025 RETAIL PERFORMANCE MEASURE REPORTS PURSUANT TO 16 TAC 25.88 - (56 filings)

APPLICATION OF EL PASO ELECTRIC COMPANY FOR AUTHORITY TO CHANGE RATES - (55 filings)

PROJECT TO DEVELOP COA AND SPCOA STATEWIDE AVERAGE SWITCHED ACCESS RATES FOR NOVEMBER 2025 PUBLICATION UNDER PURA § 52.155 AND 16 TAC § 26.223 - (50 filings)

APPLICATION OF ONCOR ELECTRIC DELIVERY COMPANY LLC TO AMEND ITS CERTIFICATE OF CONVENIENCE AND NECESSITY FOR THE DIVISION 138-KV TRANSMISSION LINE IN TARRANT AND DALLAS COUNTIES - (49 filings)