Meeting Summary - 01/06/2025 - WMWG Meeting
Grid Monitor AI | Posted 01/06/2025
▶️1 - Antitrust Admonition - Blake Holt
▶️2 - Questions on Standing Reports - WMWG Participants
- Missing reports observed, specifically forecast reports, possibly due to holidays.
- Request made to notify the WMWG Exploder when reports are posted.
- Ryan King committed to following up internally to locate missing reports and update the group.
▶️2.3 - AS Provision and Performance SOC
ASProvisionandPerformanceSOCReportDecember.pdf
- A question was raised about the AS provision and performance state of charge report.
- Unrecognized new material was noticed in the report.
- Uncertainty existed about having the correct ERCOT SMEs available to explain the content.
- Slide 3 and 4 were identified as needing further explanation.
- Ryan King was tasked with following up with Luis and his team for a response.
- There was no urgency for the item; it was suggested to revisit the discussion in February.
- The aim was to understand a trend that ERCOT might be highlighting better.
▶️3 - NPRR1256, Settlement for MRA of ESRs – Testing Question - ERCOT
- Discussion on the testing and qualification of battery capacity for constraint management within the MRA documentation.
- Explanation provided on the process of testing batteries as MRAs, similar to the testing of batteries for ancillary services.
- Clarification sought on the standard duration requirements for testing battery capacity in RFPs.
- Further inquiries about the process ERCOT uses to determine the duration requirements for RMR units.
- Confirmation that the RFP documents outline the specific duration and capacity requirements for different technologies.
- Recognition of a need for additional NPRR language to specify capacity value calculations for ESRs, including state of charge requirements.
- Discussion on the implications of ESRs not having enough state of charge during standby periods.
- Decision to table NPRR1256 for further clarifications and additional language to address capacity payment concerns.
▶️4 - NPRR1190, HDLO Provision for Increased LSE Costs – Mitigation Concept - Bill Barnes
03-1190nprr-26-tac-report-103024_bbarnes.pdf
- Discussion delayed due to timing of the meeting immediately after holidays.
- Bill Barnes has not had the opportunity to gather feedback from concerned parties such as Eric Goff.
- Suggestion to postpone further discussion for another month to allow for comprehensive feedback and amendments.
- Plan to have a more meaningful discussion in February after additional outreach.
- No further comments heard from other participants, supporting the delay.
▶️5 - NPRR1229, RTM CMP Energy Payment – Draft Comments - Lucas Turner
- Lucas Turner worked with ERCOT to clarify and revise the language of NPRR1229 to ensure ease of implementation if approved.
- Key changes include renaming to 'cost recovery payment' and updates for readability and specificity.
- Settlement formulas, titles, and conditions required for payment were clarified and restructured.
- Major changes included removing the 'real-time market opportunity costs' from the considerations and capping compensation components.
- ERCOT's plan includes three main cost components: recovery for bilateral contract costs, unit damage compensation, and startup payments.
- Manual calculation of payments will be used until system changes are implemented.
- Debate occurred over the use of High Sustained Limit (HSL) versus break-point in payments calculation; concerns of potential overcompensation were discussed.
- Startup payment logic might not align with other compensation formulas; further alignment might be needed.
- No consensus was reached on using shared caps between NPRR1229 and NPRR1190; more discussions expected.
- Some additional clarifications by ERCOT are pending for the language of NPRR1229, but they won't impact the main policy components.
- It was decided to postpone further discussion on NPRR1229 until after related conversations on NPRR1190 develop further next month.
▶️6 - CARD/CRRBA – Preview of Analysis for February Discussion - Austin Rosel
- The analysis needed for the NPRR discussion was delayed due to holidays but is expected by the February meeting.
- Katie Rich requested clarification on TCOS congestion costs and trends over 10 years, and CARD and congestion costs paid by load by zone.
- Austin Rosel mentioned they might be ready with the analysis by January 30th meeting and took note of some requested analyses.
- Discussion around historical data focused on using a recent 12-month period with suggestions to explore longer timeframes.
- Data breakdown by load class (residential, commercial, industrial) was suggested and may be included as an appendix.
- There was confusion and clarification requested on the distinction between congestion costs and congestion rent.
- Steve provided a potential method to compare load zone prices to system Lambda to determine actual congestion costs.
- The feasibility of completing the expanded analysis by January 30th was uncertain due to new analysis requests.
- Steve suggested including historical years with significant price fluctuations in the West load zone.
- Bob Whitmire noted upcoming changes with NPRR1188 affecting nodal pricing for loads.
▶️7 - Other Business – 2025 Meeting dates, Leadership - Blake Holt
- Discussion on scheduling 2025 meetings a few days before the next WMS to address coordination issues.
- Request for feedback on meeting timing and openness to adjusting schedules.
- Update on 2025 WMWG leadership nominations: Amanda Frazier for chair and Trevor Safko for vice-chair. No other nominations received.
- Introduction of Sam Fabricant to address questions regarding the State of Charge report.
- Explanation of slides related to ESR performance, unit trips, and evaluation of RRS provisioning.
- Clarification on a slide focusing on ESR performance in meeting set points for both GREDP and CLREDP sides.
- No changes noted in report data since initial findings in August.
- Open invitation for any further questions or issues to be addressed.
▶️8 - Adjourn - Blake Holt
01/08 - 9:30 AM
ERCOT - SSWG Meeting - Webex Only01/08 - 9:30 AM
ERCOT - WMS Meeting - Webex Only01/08 - 9:30 AM
ERCOT - ROS Meeting01/09 - 9:30 AM
01/07/2025
Meeting Summary - 01/07/2025 - RMS Meeting01/07/2025
The Year That Was: 2024 Energy Stocks - Winners And Losers01/07/2025
Canadian Solar to Deliver BESS and Solar to Sunrycer Projects in Texas01/07/2025
Texas, Utah, Last Energy challenge NRC’s ‘overburdensome’ microreactor regulations01/07/2025
Predictions: Regulations, Tech, Renewables Will Shape YearBROKER REGISTRATIONS - (67 filings)
APPLICATION OF CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC FOR DETERMINATION OF SYSTEM RESTORATION COSTS - (51 filings)
INDUSTRIAL CUSTOMERS' NOTIFICATION UNDER PURA SECTION §39.904 (m-1) RELATING TO NON-SUPPORT OF RENEWABLE - (49 filings)
PROJECT TO SUBMIT EMERGENCY OPERATIONS PLANS AND RELATED DOCUMENTS UNDER 16 TAC § 25.53 - (42 filings)
APPLICATION OF ENTERGY TEXAS, INC. TO AMEND ITS CERTIFICATE OF CONVENIENCE AND NECESSITY TO CONSTRUCT A PORTFOLIO OF DISPATCHABLE GENERATION RESOURCES - (34 filings)
APPLICATION OF WIND ENERGY TRANSMISSION TEXAS, LLC FOR AUTHORITY TO CHANGE RATES AND TARIFFS - (34 filings)
CY 2024 ELECTRIC UTILITY TRANSMISSION CONSTRUCTION REPORTS UNDER 16 TAC § 25.83 - (27 filings)