Oncor has 200 GW of interconnection requests, company officials say
Emma Penrod | Source: Utility DIVE | Posted 08/12/2025

About 20% of the potential demand has signed contracts or is considered “high-confidence load,” CEO Allen Nye said.
AI generated summary
Oncor Electric Delivery currently has approximately 200 GW of interconnection requests, which include significant contributions from data centers, traditional commercial and industrial customers, cryptocurrency facilities, and oil and gas operations. CEO Allen Nye indicated that around 20% of this demand has either signed contracts or is classified as 'high-confidence load.' This surge in interconnection requests could lead Oncor to revise its capital plan, potentially adding over $12 billion to its existing $36 billion plan.
Sempra's strategy to focus more on utility operations, driven by the increasing electric demand in Oncor's service area, is expected to enhance earnings and mitigate risks for investors. The company is also in the process of selling stakes in its Ecogas Mexico and Sempra Infrastructure, which are anticipated to close by mid-2026. These sales aim to bolster Oncor's expansion efforts, with Sempra expecting a greater share of its earnings to come from regulated utilities, particularly in Texas, as Oncor continues to grow its customer base and interconnection agreements.
Link to Original Article
Please find the link to the full article below. (Please note that content provider might require a paid subscription)
Source Link: https://www.utilitydive.com/news/oncor-sempra-interconnection-texas-data-center-earnings/757262/
08/13 - 9:30 AM
ERCOT - SSWG Tuning Training - Webex Only08/13 - 9:30 AM
ERCOT - PWG Meeting08/13 - 1:00 PM
PUCT - Project No . 58434, Rulemaking for Firm Fuel Supply Service08/14 - 3:00 PM
08/13/2025
ERCOT's Transmission Planning Process08/13/2025
89th Texas Legislature Summary and Market Changes08/13/2025
Longer strings, fewer inverters, lower LCOE: How 2000V solar modules reshape utility-scale project economics08/13/2025
U.S. could lose 60 GW of solar if Trump’s “start of construction” rules tighten08/13/2025
US power use to reach record highs in 2025 and 2026, EIA saysAPPLICATION OF EL PASO ELECTRIC COMPANY FOR AUTHORITY TO CHANGE RATES - (133 filings)
APPLICATION OF ONCOR ELECTRIC DELIVERY COMPANY LLC FOR AUTHORITY TO CHANGE RATES - (116 filings)
BROKER REGISTRATIONS - (84 filings)
APPLICATION OF ENTERGY TEXAS, INC. TO AMEND ITS CERTIFICATE OF CONVENIENCE AND NECESSITY FOR THE CYPRESS-TO-LEGEND 500-KV TRANSMISSION LINE IN HARDIN AND JEFFERSON COUNTIES - (60 filings)
CY 2025 RETAIL PERFORMANCE MEASURE REPORTS PURSUANT TO 16 TAC 25.88 - (47 filings)
APPLICATION OF CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC FOR DETERMINATION OF SYSTEM RESTORATION COSTS - (46 filings)
APPLICATION OF SHARYLAND UTILITIES, L.L.C. FOR AUTHORITY TO CHANGE RATES - (43 filings)