Meeting Summary - 04/29/2025 RPG Meeting
Grid Monitor AI | Posted 04/29/2025

▶️1 - Antitrust Admonition - 9:30 a.m.
▶️2 - Miscellaneous Updates
- No miscellaneous updates were provided by attendees.
▶️3 - EIR Status Update – Combined Oncor Delaware Basin Stage 5 Project & WETT Delaware Basin Stage 5 Project Alternative
EIR_StatusUpdate_Combined_Dalaware_Basin_Stage_5_Project_and_Alterntive_RPG_April_2025.pdf
- Oncor submitted the Delaware Basin stage 5 project for review estimated to cost $744.6 million, targeting a December 2029 in-service date, addressing reliability issues in the Delaware Basin due to load growth.
- WETT proposed an alternative, estimated at $305.5 million, with potential cost savings and a December 2028 target date.
- ERCOT conducted a combined independent review for both Oncor's and WETT's options.
- Preliminary results showed both options met reliability criteria with similar long-term load serving capabilities and no violations during maintenance outage analysis.
- Updated feasibility and cost assessments indicated Oncor's project at $855.3 million and WETT’s at $871 million.
- ERCOT selected Oncor’s option as it met criteria, improved long-term capability, required less CCN mileage, and was the least cost option.
- Further analyses including congestion, generation addition sensitivity, load scaling, and SSR assessment showed no significant impacts favoring the Oncor proposal.
- Future steps involve formal reports and recommendations proceeding through ERCOT's governance structures.
- Yang Zhang from WETT questioned the decision-making process, specifically highlighting load serving capability, CCN mileage, and cost differences.
- ERCOT emphasized the primary focus is on meeting reliability needs and economic solutions, indicating cost was a significant factor between the two similar options.
▶️4 - EIR Status Update – Hartring to Upland 138-kV Line and Benedum Autotransformer Addition Project
EIR_StatusUpdate_Hartring_to_Upland_and_BenedumAuto_Project_RPG_April_2025-.pdf
- Oncor and LCRA TSC submitted the Hartring to Upland 138-kV line and Benedum Autotransformer Addition Project for RPG review in August 2024.
- This is a tier two project with an estimated cost of $94 million requiring a CCN filing.
- Expected in-service date for Oncor is summer 2025, and for LCRA is June 2026.
- The project addresses post-contingency thermal and voltage violations due to significant oil and gas load growth in the area.
- ERCOT is conducting an independent review and provided a status update at the March 2025 RPG meeting.
- Preliminary results show 2 thermal violations and 10 voltage violations under N-1 contingency.
- Options 1, 3, and 4 were shortlisted for further evaluation, with Option 1 being preferred.
- Option evaluations revealed no violations for Options 1, 3, and 4, while Option 2 had 2 thermal violations.
- New Option 5 was evaluated, modifying Option 4 based on TSP feedback.
- Option 5 presents a thermal violation under N-1 contingencies.
- Long-term load serving capability was assessed for shortlisted options, with Option 1 having the highest incremental load-serving capability.
- Planned maintenance outage evaluation conducted shows no issues for Option 1, while others have thermal violations.
- Cost estimates: Option 1—$97.7 million, Option 3—$74.7 million, Option 4—$114.3 million, Option 5—$117.3 million.
- Option 1 was recommended by ERCOT, meeting reliability criteria and offering the highest load serving capability with minimal CCN mileage.
- Option 1's estimated cost is $97,700,000, with an expected in-service date of November 2025 for Oncor and May 2028 for LCRA.
- ERCOT recommends Option 1 following a congestion analysis showing no congestion issues.
▶️5 - EIR Status Update – Baytown Area Load Addition Project
EIR-CNP-Baytown_Area_Load_Addition_Project_April_RPG.pdf
- Project submitted by CNP and classified as tier one with an estimated cost of $141.65 million and a service date of January 2028.
- The project addresses thermal and voltage violations caused by a new 500 MVA load in the Baytown area related to a new customer.
- CNP and ERCOT presented project scope in November RPG; subsequent status updates provided in February and March.
- Project is currently under independent review by ERCOT.
- Violations observed include overloads on various circuits and a thermal overload on the 130 kV Grant to Herman line.
- Reliability assessment showed limited violations; plan maintenance evaluation revealed additional issues.
- Addressed 13 thermal overloads and multiple voltage violations using planning guide methodologies.
- Options evaluated for addressing violations include different combinations of transmission line upgrades and substation enhancements across various regions of Houston.
- Option 1 focuses on Midtown with upgrades in Grant to Herman line and specific substation enhancements.
- Option 2 involves broader upgrades across Midtown, Baytown, Southeast Houston, and North Houston.
- Option 3 mirrors Option 2 except for Baytown differences, focusing on extending double circuit 345-kV lines.
- Timeline anticipates final recommendation by Q2 and readiness for board consideration in June.
- No questions or concerns were raised by attendees.
▶️6 - EIR Status Update – Texas A&M University System RELLIS Campus Reliability Project
EIR-BTU-Texas-A-M-University-System-RELLIS-Campus-Reliability-Project-Status-Update-RPG-Apr-2025.pdf
- The RELLIS Campus Reliability Project is a tier one project with a cost estimate of $271.5 million, requiring a CCN. The estimated in-service date is May 2029.
- ERCOT conducted a reliability need analysis driven by a new confirmed load of 378 MW in 2030. The analysis revealed multiple reliability violations in various competency conditions including low voltage and thermal overloads.
- Four options were studied to resolve the reliability violations. Option 1 involves expanding the existing RELLIS substation and adding a 345 kV double circuit line from TNP One to RELLIS. Other options involved different configurations of lines from TNP One, Sandow, and Salem to RELLIS.
- Options 1, 2, and 4 resolved all reliability violations under particular conditions, making them shortlisted for further evaluation. Option 3 had remaining overloads.
- Further evaluations will continue including long-term load serving capability assessments, cost estimates, and feasibility assessments. Final recommendations are expected by the end of the year.
- No questions were raised during the meeting.
▶️7 - EIR Status Update – Aransas Pass to Rincon 69-kV Line Rebuild Project
EIR_AEPSC_Aransas_Pass_to_Rincon_Project_Final_Update_RPG_April_2025.pdf
- The project was submitted in November 2024 as a tier two project, estimated at $33 million, requiring a CCN, with an in-service date of June 2026.
- The project addresses post-contingency thermal overloads in San Patricio County.
- ERCOT provided updates in previous RPG meetings, and the project is under independent review.
- Three options were presented to address thermal violations identified from Gregory to Aransas Pass.
- Option 1 involves rebuilding the existing Aransas Pass to Gregory 69-kV line to a 138-kV standard, with ratings of 239 MVA for 8.5 miles, including a 0.03-mile segment from Gregory to Rincon.
- Option 2 includes building a new Gregory to Gibbs 138-kV line, costing $52 million and requiring 1.36 miles of CCN.
- Option 3 involves building a new Ingleside - DuPont switch to Ingleside 138-kV double circuit line, costing $48 million and requiring 3.25 miles.
- All options were feasible and met ERCOT's reliability criteria, improving long-term load-serving capability.
- Option 1, costing $34 million and requiring one mile of CCN, is ERCOT's preferred option due to its cost-effectiveness and minimal CCN mileage.
- A congestion analysis showed no new congestion for the preferred option within the study area.
- The preferred option is to be completed by June 2026, with an EIR report to be posted in May.
- No questions were raised after the presentation.
▶️8 - EIR Status Update – Roscoe Area Upgrades
EIR-Oncor-Roscoe-Area-Upgrades-Project-StatusUpdate-April_2025_RPG.pdf
- Oncor submitted the Roscoe area upgrades project for RPG review in December 2024 with an estimated cost of $83 million and expected in-service date of June 2028.
- The project's main purpose is to address voltage violations observed by Oncor in the West weather zone, Nolan County.
- Project upgrades include enhancing the path from Eskota to Oak Creek, Oak Creek to Nolan, and Nolan to Sweetwater from 69-kV to 138-kV and constructing a new 138-kV line from Sweetwater Creek to Kilgore.
- Four project options were evaluated for addressing voltage violations, with options one and four shortlisted for further evaluation due to no thermal or power flow violations.
- Option one is Oncor's proposal, and option four includes constructing a new substation tapping between the Champion Creek to Oak Spring 345-kV line.
- Option three was deemed infeasible, and option two exhibited a thermal violation.
- Both shortlisted options showed improved long-term load serving capability and no voltage violations during planned maintenance outage evaluations.
- Next steps include further evaluation of options, feasibility assessments, and cost estimates with updates provided in the next RPG meeting and final recommendations reported by May.
- No questions were raised from the participants.
▶️9 - Southern DFW Load Interconnection and General Grid Strengthening Project Overview
Oncor_Southern-DFW-Load-Interconnection_Project_RPG_04292025.pdf
- Project is a tier one initiative spanning multiple counties, primarily driven by 4,064 MW of new load in the Southern DFW area.
- Aim: Resolve thermal and voltage violations, provide additional 345-kV sources, enhance load serving capacity, and improve system reliability.
- Project will include new switching stations and transformer installations, with extensive circuit miles upgrades.
- Estimated cost: $1.219 billion; completion anticipated between 2026-2028.
- Analysis on feasibility of line outages is ongoing; staggered construction scheduled between 2026 and 2028.
- Implemented both peak and off-peak cases in planning to address possible challenges with switching capacitor banks.
- Reactive compensation, including STATCOMs and capacitors, planned to support the new load.
- Questions raised regarding feasibility, load assumptions, and prioritization of projects in response to anticipated service dates.
- Clarifications on load types and agreements, addressing loads predominantly from data centers or cryptos.
- Discussion on storage capability and design standards for load connections.
▶️10 - ERCOT Independent Review Scope: Southern DFW Load Interconnection and General Grid Strengthening Project
EIR_Scope_Oncor_Southern_DFW_Load_Interconnection_Project_-_RPG_April_2025.pdf
- The focus is on the transmission elements in various counties in the North, Central, and East weather zone, using a base case from the 2024 RTP and 2029 summer peak load case.
- Projects within the study area before December 2028 will be included unless they're already in the case; some are listed in appendix A1.
- Transmission projects identified as placeholders in the 2024 RTP will be removed, with a list available in appendix A2.
- New generation with a service date before December 2028 will be added if not already modeled, as per the 2025 March GIS report.
- Generation dispatch will be consistent with the 2024 RTP, and recently retired units will be reviewed.
- Study area load adjusted to project submissions while maintaining reserves consistent with the 2024 RTP.
- Standard contingencies will follow NERC and ERCOT guidelines, and specific plants and transformers were listed for testing.
- Reliability analysis, maintenance outage evaluation, and long-term load capability assessment will be executed.
- Project validity will lead to additional analysis like sensitivity, SSR assessment, and congestion analysis.
- Updates will be provided in future RPG meetings with final recommendations tentatively scheduled for Q3 2025.
▶️11 - Hamilton County Conversion Project Overview
- The project spans across Comanche County, Hamilton County, Coryell County, and into Bell County.
- Brazos Electric is responsible for a long 69-kV transmission line in this corridor.
- Project begins at Hasse Substation with a 138-kV source and will move south to Gustine-Indian Gap transmission line.
- A CCN application required due to limited existing easements, additional easements are being acquired.
- Full voltage conversion planned due to a transmission constraint.
- Grizzly Ridge site has a generator limited to 70 MW, although capable of 110 MW.
- Two official projects are connecting to the grid: Grizzly Ridge and another 100 MW solar farm.
- There have been several load inquiries, but many are put off by potential delays for full service capability.
- Brazos Electric is concerned about potential future voltage violations due to load growth.
- Goal is to perform a full voltage conversion from Hasse to Poage (soon to be replaced by Crusader station).
- The project description is submitted and available on the ERCOT MIS site, though not with meeting materials.
- No additional comments or questions from the room attendees.
▶️12 - ERCOT Independent Review Scope: Hamilton County Conversion Project
EIR_BEC_Hamilton_County_Conversion_Project_SCOPE_APRIL.pdf
- The project is a tier two project estimated to cost $90 million, requiring CCN with an estimated in-service date of fall 2030.
- It is recommended as a GTC exit strategy for the Hamilton GTC.
- Project involves converting multiple 69-kV to 138-kV pathways in between Hasse and Poage and involves various substations and transmission lines.
- They will rebuild certain segments as double circuits with specified MVA ratings.
- Study assumptions include focusing on the North Central weather zone, and using the 2024 RTP 2030 summer peak case.
- Economic study will also be conducted using the 2024 RTP economic study base case for 2029.
- Needed analysis will include both reliability and economic analysis, project evaluation will test alternatives, and planned maintenance and congestion analysis will be conducted.
- Final project recommendation expected in Q2 of this year.
- Question about additional generation for Brazos interconnecting with the project area will be updated in the April GIS report.
- GTC exit strategy option is studied as a project alternative.
▶️13 - Update on Financial Assumptions for ERCOT Economic Planning Criteria
Financial-Assumptions-Update-for-ERCOT-Economic-Planning-Criteria_2025RTP_v1.0.pdf
- ERCOT performs two required tests for economic projects, namely the congestion cost savings test and the production cost savings test, as per PUCT substantive rules.
- A transmission project is considered economically viable if it passes either of these tests.
- The congestion cost savings test evaluates if consumer energy cost savings exceed the average of the first three years' annual revenue requirement.
- The production cost savings test assesses if annual production cost savings exceed the first year annual revenue requirement.
- Nodal protocol sections 3.11.2(5) and 3.11.2(6) necessitate annual reviews of financial assumptions used to determine revenue requirements.
- Revenue requirement calculations for TSPs cover the return on rate base (cost of equity and debt and debt to equity ratio), depreciation, O&M costs, and taxes.
- The current financial assumptions methodology in use is consistent with that used in 2024.
- The methodology employs a generic transmission project with assumed capital cost for each TSP to calculate revenue requirements.
- Results show a side-by-side comparison of first year and average first three years' revenue requirements for each TSP.
- Weighted first year annual revenue requirement is at 13%, and the average for the first three years is 12.7% for this year.
- Questions were addressed regarding the economic criteria tests and the generic baseline project used for calculations.
▶️14 - Long-Term Load Forecast
Long-term-Load-Forecast-RPG.pdf
- Discussion on various components of the forecast including base economic forecast, electric vehicle (EV), crypto, and rooftop solar forecasts.
- Explained the methodology of the 'waterfall approach' to read forecasts.
- Winter storm Uri scenario analysis included to understand impact on forecasts.
- Economic outlook reflects a positive linear trend for residential and business premises growth.
- EV forecast growth is slower than expected due to lack of sales, with detailed charging patterns considered for different zones.
- Crypto forecast includes a new large flexible load profile with observed patterns from previous years.
- Rooftop solar forecast has a model based on per customer usage with weather and calendar variables.
- Annual energy and peak relationship shows demand response increases during summer, slowing peak growth compared to annual energy.
- New forecast methodologies emphasize officer letters and contracts, indicating substantial data center load growth.
- Questions addressed on data center load ramp-up, officer letter loads methodologies, and data transparency.
- ERCOT mentioned ongoing studies and collaboration with stakeholders to refine load forecasts and understand the grid impact.
- Acknowledgment of the challenges posed by moving target forecasts and the need for transparency and consistency in processes.
▶️15 - Adjourn
04/30 - 8:00 AM
LEGE - House Natural Resources04/30 - 8:00 AM
LEGE - House 89th Legislative Session04/30 - 10:00 AM
ERCOT - 25SSWG Post-dispatch Tuning04/30 - 9:30 AM
04/30/2025
The Key to More Clean Energy? Wasting Less of It04/30/2025
Solar cell production expected to double in the U.S. in less than two years04/30/2025
Restrictions on wind, solar unpopular among Texas Republicans: Poll04/30/2025
Can AI chips make the grid smarter? Utilidata raises $60M to find out.04/30/2025
Clean energy manufacturers cancel projects as Trump-era policies take holdAPPLICATION OF ENTERGY TEXAS, INC. TO AMEND ITS CERTIFICATE OF CONVENIENCE AND NECESSITY FOR THE SETEX AREA RELIABILITY PROJECT IN JASPER, MONTGOMERY, NEWTON, POLK, SAN JACINTO, TRINITY, TYLER, AND WALKER COUNTIES - (287 filings)
APPLICATION OF CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC FOR APPROVAL OF ITS 2026-2028 TRANSMISSION AND DISTRIBUTION SYSTEM RESILIENCY PLAN - (87 filings)
CY 2024 ANNUAL POWER LINE INSPECTION & SAFETY REPORT IN PURSUANT TO 16 TAC § 25.97(F) - (82 filings)
APPLICATION OF EL PASO ELECTRIC COMPANY FOR AUTHORITY TO CHANGE RATES - (80 filings)
BROKER REGISTRATIONS - (70 filings)
APPLICATION OF CROSS TEXAS TRANSMISSION, LLC FOR AUTHORITY TO CHANGE RATES AND TARIFFS - (54 filings)
COMPLAINT OF VALERO REFINING-TEXAS, LP AGAINST TEXAS-NEW MEXICO POWER COMPANY - (53 filings)