Meeting Summary - 04/16/2025 RIWG Meeting

Grid Monitor AI | Posted 04/16/2025

Related controls:
Keyword Tags:

▶️1 - Antitrust Admonition

▶️2 - RIOO-Update

ERCOT-RIWG-2025-April-RIOO-1.pdf

  • Introduction of high level changes to the RIOO application currently in production.
  • New questions added to the substation panel to capture information on industrial generation facility designation, applicable for private use networks.
  • For operational generators, default selections applied for the new questions.
  • A new question introduced on the unit details panel to capture self generator PUCT registration status, required on UIS but not on URS.
  • Addition of a radio button in devices, MLSE, and MPT data panels to allow skipping the relay loadability rating if not known.
  • Label change on the unit solar inverter panel for clarity, renamed to 'base MVA for transformer in MVA'.
  • New SSR required flag added for the INR TSP view and ‘TSP key milestones’ tab.
  • Changes related to the load resources on the RIOO-RS side based on feedback, with stopped LRs hidden on the form but can be selected to view the data.
  • Confirmation that the updates are currently live in production and were released as part of R3.

▶️3 - NOGRR245 Update

RIWG_April_2025_NOGRR245_Update.pdf

  • The NOGRR245 deadline to submit extension or exception requests was moved to April 15, 2025.
  • Existing units must complete maximization by December 31, 2025.
  • Different deadlines for frequency and voltage ride-through extensions: frequency by December 31, 2027, and voltage by December 31, 2028, depending on ERCOT granting the extension.
  • ERCOT is currently validating and reviewing submitted data and will develop a scope for the exception process by July-August 2025.
  • NOGRR245 exception studies are planned for September-October, with notifications in November-December 2025.
  • The exemption process timeline might adjust based on rulemaking from the PUC and the number of submissions received.
  • Incomplete submissions must be addressed within ten business days upon notification from ERCOT.
  • ERCOT's decision on extension requests to come within 180 days, with options to notify of extended review timelines if necessary.
  • Participants can appeal ERCOT's decisions to the PUC.
  • Approximately 500 resources intended for maximization by December 31, 2025, with various extension and exemption requests noted.
  • Obligations for resources not submitting exception/extensions by April 15 include meeting frequency and voltage ride-through requirements by December 31, 2025, or synchronization/operation dates.
  • Clarification that requirements apply only to transmission connected resources, not distribution connections.

▶️4 - Subsynchronous Ferroresonance Issues

  • Verbal update on subsynchronous ferroresonance (SSFR) concerning interactions between main power transformers and series capacitors.
  • SSFR has become more prevalent and poses risks during backfeed energization when transformers are brought online.
  • A current issue is the late completion of SSR studies impacting project timelines.
  • Consideration for conducting SSR studies before part one of backfeed energization.
  • Installing protection relays on transformers is not an ideal solution due to ride-through requirements.
  • Recommendation for using transformers with higher saturation curves and early SSR studies.
  • Questions arose regarding inverter instability with shunt capacitors, responsibility of resource entities to consider such interactions.
  • Information available on locations of series capacitors within ERCOT through previous presentations and MIS access.
  • SSFR issues typically arise with radial connections or plants tapping serious compensated lines.
  • Guidance on preferable saturation curves suggests above 1.2 per unit for transformers.
  • Technical note: Subsynchronous currents can saturate transformers easily due to slower rate of change of current.

▶️5 - Dynamic Models – Power Plant Controller Issues

Templates-and-Declaring-the-PPC.pdf

  • Discussion on the importance of submitting a proposed modification request before changing field settings, following ERCOT's Planning Guide 5.5(6).
  • Introduction of the updated dynamic model template, due for submissions starting June 1, 2025.
  • Focus on issues with interconnecting entities selecting power plant controllers late in the process, causing problems if the controller does not pass MQT tests.
  • Announcement that starting next week, entities must declare their power plant controller when submitting a model.
  • Clarification that models submitted and accepted without declaring a power plant controller won't need updates, but any new submissions must include this information.
  • Emphasis on the potential need for restudy if declared models differ significantly from earlier submissions.
  • Discussion on the importance of ensuring the power plant controller can pass all required tests and matching the declared performance in later stages.
  • Concerns raised on communication delays affecting the dynamic reactive response of power plant controllers.
  • Highlighting the need for accurate PSCAD modeling accounting for data measurement and command update constraints.
  • Consideration of disallowing generic models in PSCAD due to their limitations in accurately reflecting site-specific constraints.
  • Encouragement of accurate submissions taking into control speeds and communication lags.

▶️6 - Running AVR, PFR Tests in MQT

Running-AVR-PFR-Tests-in-MQT.pdf

  • Discussion on running Automatic Voltage Regulator (AVR) and Primary Frequency Response (PFR) tests within Model Quality Tests (MQT).
  • Currently a recommendation, but may become a future requirement.
  • Issues identified where tuning during AVR tests affects MQT results, leading to non-compliance with voltage ride-through requirements.
  • Recommendation to model AVR and PFR performance during MQT to ensure compliance before entering the Queue Service Agreement (QSA).
  • Suggested short circuit ratio of about five, as detailed in the DWG procedure manual, section 3.1.5.8.
  • ERCOT will review AVR and PFR test simulations submitted in MQT and provide feedback.
  • No current impact on QSA acceptance, but recommended due to existing commissioning issues.
  • Discussion on hardware suitability—if unable to meet both AVR and MQT requirements, the hardware may be inappropriate.
  • Plants often delay AVR testing until online, leading to excessive adjustments; early simulation advised.
  • Acknowledgment of plant-specific constraints and real-world limitations do exist.
  • Emphasis placed on early verification of control and hardware capability.
  • Acknowledgment that performance requirements are based on grid stability necessities.
  • Difference in control adaptability discussed between wind facilities (typically more adaptable) versus solar and battery facilities.

▶️7 - GINR Topics

ResourceIntegrationWorkshop_GINR_Topics_04162025.pdf

  • May 1 QSA deadline: All requirements must be met by May 1, 2025. The 45-day deadline for projects is March 17.
  • EPS meter design proposal needs to be submitted before ERCOT approves full registration data. This affects projects aiming for future production load dates.
  • New EIA reporting requirement: ERCOT must submit EIA-930A, detailing generator inventory. Three new EIA fields will be added to RIOO-IS and RIOO-RS starting April 24, 2025.
  • EIA fields: Recommended completion before full registration data approval for projects without approved production load dates. Proposing mandatory inclusion in registration glossary revision.
  • Clarification on procedures: EPS meter design proposal must be submitted 90 days before production workday, not just prior to PLD.
  • Discussion on EIA-860 form: Completion depends on certain criteria, such as SGIA assigned notice to proceed.
  • NPRR1272: Update on voltage support and private use network revision request.
  • Commissioning requests for parts 1-3 must be submitted to the designated commissioning request inbox.
  • There are over 2,000 generation interconnection requests totaling about 405 gigawatts. Small generation consists of 26 non-model ready and 50 model-ready projects.
  • For queries, reach out to the resource integration department at ResourceIntegrationDepartment@ercot.com.
  • Next meeting is scheduled for June 10, 2025.

8 - Other Topics

  • Not Discussed

▶️9 - Adjourn  

Create a free trial account: Sign Up

Grid monitor is free to try. No credit card required


Already have an account? Login

Most Active PUCT Filings

APPLICATION OF ENTERGY TEXAS, INC. TO AMEND ITS CERTIFICATE OF CONVENIENCE AND NECESSITY FOR THE SETEX AREA RELIABILITY PROJECT IN JASPER, MONTGOMERY, NEWTON, POLK, SAN JACINTO, TRINITY, TYLER, AND WALKER COUNTIES - (191 filings)

APPLICATION OF EL PASO ELECTRIC COMPANY FOR AUTHORITY TO CHANGE RATES - (121 filings)

CY 2025 RETAIL PERFORMANCE MEASURE REPORTS PURSUANT TO 16 TAC 25.88 - (119 filings)

BROKER REGISTRATIONS - (88 filings)

APPLICATION OF CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC FOR APPROVAL OF ITS 2026-2028 TRANSMISSION AND DISTRIBUTION SYSTEM RESILIENCY PLAN - (69 filings)

CY 2024 ANNUAL POWER LINE INSPECTION & SAFETY REPORT IN PURSUANT TO 16 TAC § 25.97(F) - (57 filings)

PROJECT TO SUBMIT EMERGENCY OPERATIONS PLANS AND RELATED DOCUMENTS UNDER 16 TAC § 25.53 - (55 filings)