Just Can't Get Enough - Texas Preps to Meet Surging Power Demand from Data Centers, Crypto Miners

Lisa Shidler | Source: RBN Energy | Posted 12/06/2024

Keyword Tags:

Texas is the fastest-growing state for electricity consumption in the nation and the Electric Reliability Council of Texas (ERCOT), which is responsible for about 90% of the state’s electricity service, said earlier this year that peak power demand could nearly double in just six years


AI generated summary

With Texas experiencing a rapid growth in electricity consumption due to factors such as data centers, artificial intelligence, cryptocurrency mining, population growth, and rising temperatures, the state's Electric Reliability Council (ERCOT) has projected a potential doubling of peak power demand by 2030. While renewable energy sources have been on the rise, Texas heavily relies on natural gas-fired power to meet its electricity needs, and the state's energy industry hinges on reliable power sources. Known for its unique energy-only wholesale market and stand-alone grid status, Texas faces challenges in balancing power demand, especially during extreme weather events like Winter Storm Uri.

As the Lone Star State grapples with an escalating need for electricity driven by population growth and increasing temperatures, the Public Utility Commission of Texas anticipates a 67% rise in the state's population by 2050. A report by the Office of the Texas State Climatologist at Texas A&M University highlights the escalating occurrences of 100-degree days and projects a fourfold increase in such days by 2036 compared to the 1970s levels. Despite efforts to strengthen the power grid, ERCOT acknowledges a slightly higher grid reliability risk due to mounting power demand, underscoring the ongoing struggle to meet the state's growing appetite for power amidst unique market dynamics and environmental challenges.



Link to Original Article

Please find the link to the full article below. (Please note that content provider might require a paid subscription)


Source Link: https://rbnenergy.com/just-cant-get-enough-texas-preps-to-meet-surging-power-demand-from-data-centers-crypto-miners

Create a free trial account: Sign Up

Grid monitor is free to try. No credit card required


Already have an account? Login

Most Active PUCT Filings

BROKER REGISTRATIONS - (87 filings)

JOINT APPLICATION OF THE CITY OF SAN ANTONIO, ACTING BY AND THROUGH THE CITY PUBLIC SERVICE BOARD (CPS ENERGY), AND SOUTH TEXAS ELECTRIC COOPERATIVE, INC. (STEC) TO AMEND THEIR CERTIFICATES OF CONVENIENCE AND NECESSITY FOR THE PROPOSED HOWARD ROAD-TO-SAN MIGUEL 345-KV TRANSMISSION LINE IN BEXAR AND ATASCOSA COUNTIES - (58 filings)

APPLICATION OF CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC FOR DETERMINATION OF SYSTEM RESTORATION COSTS - (44 filings)

APPLICATION OF ENTERGY TEXAS, INC. TO AMEND ITS CERTIFICATE OF CONVENIENCE AND NECESSITY TO CONSTRUCT A PORTFOLIO OF DISPATCHABLE GENERATION RESOURCES - (34 filings)

APPLICATION OF WIND ENERGY TRANSMISSION TEXAS, LLC FOR AUTHORITY TO CHANGE RATES AND TARIFFS - (31 filings)

APPLICATION OF ENTERGY TEXAS, INC. TO AMEND ITS CERTIFICATE OF CONVENIENCE AND NECESSITY TO CONSTRUCT A PORTFOLIO OF RENEWABLE GENERATION RESOURCES - (31 filings)

CY 2024 ELECTRIC UTILITY TRANSMISSION CONSTRUCTION REPORTS UNDER 16 TAC ยง 25.83 - (30 filings)