ERCOT Working To Use CenterPoint-TDU Mobile Generation As Alternative To RMRs for Two CPS Units; Will Recommend RMR Agreement For One CPS Unit
Paul Ring | Source: Energy Choice Matters | Posted 11/25/2024
ERCOT reported at today's Texas PUC opening meeting that it is working on developing an agreement to move the mobile generation units of CenterPoint Energy Houston Electric from Houston to the San Antonio area, as an alternative to entering into reliability must-run agreements with two CPS Energy units which will suspend operations
AI generated summary
ERCOT is actively working on an agreement to relocate the mobile generation units of CenterPoint Energy Houston Electric from Houston to the San Antonio area as an alternative to initiating reliability must-run agreements with two CPS Energy units that are set to suspend operations. This shift would involve addressing feasibility, regulatory, and cost considerations.
The mobile generation capacity of approximately 500 MW from CenterPoint Energy Houston Electric matches the combined capacity of the two aging CPS Energy Braunig units that are slated for suspension, Units 1 & 2. ERCOT is temporarily setting aside the need for a reliability must-run agreement for Units 1 & 2 to focus on exploring the potential use of mobile generation from CEHE, with discussions ongoing with relevant parties to evaluate technical and cost aspects of this proposed solution.
Link to Original Article
Please find the link to the full article below. (Please note that content provider might require a paid subscription)
Source Link: http://www.energychoicematters.com/stories/20241121e.html
11/26 - 3:00 PM
ERCOT - ERCOT observed holiday as defined by Protocol Section 211/28 - 12:00 AM
ERCOT - ERCOT observed holiday as defined by Protocol Section 211/29 - 12:00 AM
ERCOT - Technology and Security Committee Meeting12/02 - 8:30 AM
11/25/2024
US Grid Operators Kept the Lights on This Summer with More Solar, Storage, & Wind11/25/2024
The Texas grid is ready for winter, ERCOT CEO says11/25/2024
DOE Awards $2.2B to Two Regional Hydrogen Hubs11/25/2024
FERC modifies rule to give states more participation in long-term regional transmission planning11/25/2024
North Plains Connector: A bipartisan solution to America’s energy grid challengesJOINT APPLICATION OF THE CITY OF SAN ANTONIO, ACTING BY AND THROUGH THE CITY PUBLIC SERVICE BOARD (CPS ENERGY), AND SOUTH TEXAS ELECTRIC COOPERATIVE, INC. (STEC) TO AMEND THEIR CERTIFICATES OF CONVENIENCE AND NECESSITY FOR THE PROPOSED HOWARD ROAD-TO-SAN MIGUEL 345-KV TRANSMISSION LINE IN BEXAR AND ATASCOSA COUNTIES - (145 filings)
CY 2024 RETAIL PERFORMANCE MEASURE REPORTS PURSUANT TO 16 TAC 25.88 - (118 filings)
APPLICATION OF TEXAS-NEW MEXICO POWER COMPANY FOR APPROVAL OF A SYSTEM RESILIENCY PLAN - (70 filings)
BROKER REGISTRATIONS - (42 filings)
CY 2024 POWER MARKETER RE-REGISTRATION PURSUANT TO 16 TAC 25.105 (D) - (37 filings)
APPLICATION OF AEP TEXAS INC. FOR APPROVAL OF A SYSTEM RESILIENCY PLAN - (32 filings)
INFORMATIONAL FILING OF ERCOT INTERCONNECTION AGREEMENTS PURSUANT TO SUBST. R. §25.195(e) - (30 filings)